What Does the Excavation Time Calculator Do?
The Excavation Time Calculator takes the following inputs:
- Excavation Volume (m³): The total volume of soil or material to be excavated.
- Excavation Rate (m³/hour): The rate at which the machine or equipment excavates per hour.
- Cost per Hour ($): The cost of operating the excavation equipment per hour.
Outputs:
- Excavation Time: The total time required to complete the excavation.
- Total Cost: The overall cost of the excavation process.
Formula for Excavation Time
The formula to calculate the Excavation Time is:
Excavation Time=Excavation RateExcavation Volume
Where:
- Excavation Volume = Total material to be excavated (in cubic meters, m³).
- Excavation Rate = Rate of excavation per hour (m³/hour).
Formula for Total Cost
Once the excavation time is calculated, the Total Cost can be determined using the formula:
Total Cost=Excavation Time (hours)×Cost per Hour ($)
Where:
- Excavation Time = Time calculated from the previous formula (in hours).
- Cost per Hour = Operating cost of the excavation equipment (in dollars per hour).
Example Calculation
Let’s assume the following values:
- Excavation Volume: 300 m³
- Excavation Rate: 50 m³/hour
- Cost per Hour: $100
Step 1: Calculate Excavation Time
Using the formula:
Excavation Time=Excavation RateExcavation Volume
Substitute the values:
Excavation Time=50300=6hours
Step 2: Calculate Total Cost
Now calculate the total cost using the formula:
Total Cost=Excavation Time×Cost per Hour
Substitute the values:
Total Cost=6×100=600$
Final Results:
- Excavation Time: 6 hours
- Total Cost: $600
Frequently Asked Questions
What is excavation rate?
Excavation rate is the volume of soil, rock, or other material removed in a given time. It is commonly measured in cubic meters per hour (m³/hr) or cubic yards per hour (yd³/hr).
What measurements do I need?
Enter the total excavation volume, the equipment productivity rate, and the number of working hours planned per day.
Should volume and productivity use the same unit?
Yes. For example, use cubic yards with cubic yards per hour, or cubic meters with cubic meters per hour.
Does working hours per day change total excavation hours?
No. It changes the estimated number of workdays. Total operating hours are based on excavation volume and equipment productivity.
Can I use this calculator for multiple machines?
Yes. Add the combined productivity rates of machines that can work efficiently at the same time, then use that total rate in the calculator.
Why may actual excavation take longer?
Actual time can be affected by soil type, rock, weather, equipment downtime, operator availability, site access, hauling distance, utilities, permits, and safety requirements.
Is this result a final project schedule?
No. It is a planning estimate. Add time for setup, mobilization, surveying, hauling, grading, inspections, and unexpected site conditions.